Ministers have cleared a 1.5-million-panel scheme that will tie with a Lincolnshire project as Britain’s largest solar farm, despite opposition from the town’s MP and most respondents to an early public consultation.
The Government has granted development consent for the Great North Road Solar and Biodiversity Park, an 800-megawatt scheme that will place about 1.5 million solar panels in a broken ring around a cluster of villages north-west of Newark. The consent was confirmed by the Department for Energy Security and Net Zero on Tuesday, and the final decision was signed off by Baroness Curran, a Parliamentary Under-Secretary of State. It came a day before the deadline: the Energy Secretary had until October 28 to rule on the application.
The approval places the Nottinghamshire scheme among the largest renewable projects consented in Britain. It becomes the joint-largest solar farm in the country, matching the 800MW Springwell Solar Farm across the Lincolnshire border in North Kesteven, which received permission in April. The developer, Elements Green, says the park could supply enough electricity for 400,000 homes, more than the total number of households in Nottinghamshire.
The panels are to be grouped into what the developer calls “solar islands”. They will stretch roughly 6.2 miles (10km) from north to south around villages including Caunton and Ossington, with the eastern edge running beside the A1. Bathley and Norwell are also inside the ring, on agricultural land north-west of the town. The site covers nearly 4,000 acres. Alongside the arrays, the consent covers a battery energy storage system and grid connection infrastructure. Elements Green has said it chose the location because National Grid’s Staythorpe substation had connection capacity, freed up by the closure of fossil fuel power stations.
Because of its size, the project never came before Newark and Sherwood District Council. Its classification as nationally significant infrastructure meant consent had to be sought through the Planning Inspectorate. The application was submitted on 27 June 2025 and accepted for examination in July that year. The examination ran from November 2025 to April 2026.
The Examining Authority’s report concluded that the identified harms, covering landscape and visual impact, agricultural land, traffic, cultural heritage, noise and cumulative effects, did not outweigh the scheme’s benefits. The decision was not automatic: in August, the Energy Secretary asked for further information before ruling, having received the inspectors’ recommendations on July 28. In a statement on Tuesday, the Government said the examiners had “gave full consideration to all local views” before reporting to ministers.
Local opposition has been persistent. A consultation whose results were published in 2024 found that 54% of respondents opposed the scheme. Robert Jenrick, Newark’s MP, has campaigned against it since it was unveiled in 2023. Now sitting for Reform UK, he said he was dismayed by the decision, felt residents’ views had been ignored, and noted that more than a tenth of his constituency would now be given over to solar. “Good farmland ruined. Years of mess and disruption. Views wrecked for generations,” he said.
The scale of his objection reflects more than one scheme. In a Commons debate in September 2025, Mr Jenrick set Great North Road alongside two other proposals in his seat, the One Earth project and the Steeple renewables scheme, arguing that together they would cover at least 9% of the constituency. A local objectors’ group cited the loss of high-quality farmland, flood risk, construction routes and site selection among its grounds for opposing the project.
Elements Green has presented the scheme as a mixed land use. Sheep are to graze among the panels, and the company has worked with the RSPB, Nottinghamshire Wildlife Trust and other conservation groups. It has promised more than 60,000 new trees, over 800 acres of biodiversity areas and more than 50km of hedgerow, along with new permissive footpaths and six bridleways. A £1m community fund for projects in the affected area also forms part of the proposals. The developer has previously estimated that the park would pay between £1.5m and £3m a year in business rates to the district.
The decision can still be challenged. Opponents have six weeks to ask the High Court to consider whether there are grounds for a judicial review. If no challenge succeeds, work could begin within about a year: Elements Green’s published timetable indicated that construction would start no earlier than 2027.