The agency will review an 18-week programme due to start at Nottingham Knight in January, after a petition drew more than 5,000 signatures and Rushcliffe’s council leader called for the work to stop.
National Highways has agreed to review the next phase of its roadworks on the A52 south of Nottingham, after drivers reported that journeys of around 25 minutes were taking up to an hour and a half and local politicians called for the work to be halted.
The undertaking followed a meeting on Thursday between the agency’s project team, James Naish, the Labour MP for Rushcliffe, and Hetvi Parekh, the borough councillor for Edwalton. According to Cllr Parekh, the agency acknowledged that lessons had to be learned and agreed to re-examine, with its contractor, an 18-week programme of utility and enabling work at Nottingham Knight roundabout scheduled for January.
The concession matters because the disruption so far has come from preparatory work alone. Full construction on the A52 Nottingham Junctions scheme, which will rebuild the Nottingham Knight and Wheatcroft roundabouts, has yet to start, and National Highways expects the project to continue until spring 2029.
The two roundabouts lie about 1.6km apart on the southern edge of the city and are among the busiest junctions on the route; figures published by Nottinghamshire County Council put daily traffic at roughly 64,000 vehicles at Nottingham Knight and 50,000 at Wheatcroft. Lane closures and a 40mph limit have been in place while utility and telecoms companies move cables and pipes beneath Wheatcroft Island. Because the A52 carries traffic between Nottingham, Radcliffe-on-Trent, Bingham and Grantham, the queues have reached well beyond the works themselves.
Cllr Parekh’s petition, which asks National Highways to lift restrictions once they are no longer needed and to communicate more clearly about closures, passed 3,400 signatures within hours of its launch and exceeded 5,000 by early Thursday, according to the West Bridgford Wire. Signatories describe a five-mile commute from Keyworth into the city centre taking almost an hour and a half, and a Queen’s Medical Centre nurse who spent three hours travelling to and from work on Monday and still arrived late for a clinic. A business owner at Edwalton Business Park said staff were losing about half an hour on each journey.
On Wednesday Neil Clarke, the Conservative leader of Rushcliffe Borough Council, wrote to the Transport Secretary, National Highways, Mr Naish and the leader of Nottinghamshire County Council asking for the works to be suspended immediately and their methods reviewed. The road is managed by National Highways, not by the borough or the county. “People can’t get to work, they can’t get their kids to school,” Cllr Clarke said.
National Highways has defended its approach on safety grounds. Adam Gallis, its senior project manager, said the closures and lower speed limit protected workers and allowed the A52 to stay open, and that repeatedly removing and reinstating traffic management during this phase would be neither safe nor efficient. “Our aim is always to minimise disruption,” he said, adding that schemes are monitored and reviewed as work progresses.
Many complaints have focused on cones left in place when nobody appears to be working. The agency says much of the activity is underground. Cllr Parekh said officials told Thursday’s meeting that some excavations run alongside high-pressure gas mains and electricity cables, so work areas cannot simply be reopened at the end of each shift.
The scheme was first set out in the government’s 2014 Road Investment Strategy, and earlier improvements at the Nottingham Road and Cropwell Road junctions opened in 2017. When Griffiths Farrans Joint Venture was appointed in 2023 to build the final two junctions under a £52.5m contract, work was expected to start in September 2024 and finish in 2026 or 2027. A public inquiry was held in July 2025, and the Transport Secretary approved the compulsory purchase and side roads orders that November. The redesign converts both roundabouts into “through-abouts”, with lanes cutting across the centre.
In the near term, current work at Nottingham Knight was due to finish this week, with about two more weeks of utility work at Wheatcroft that could stretch to three, according to Cllr Parekh. National Highways has said there should be no major daytime restrictions on the scheme in December. Separately, overnight closures between Bottesford and Barrowby, with a diversion via the A46 and A1 through Newark, are affecting drivers heading towards Grantham this week.
Cllr Parekh said she and Mr Naish had made clear that “we cannot simply repeat the level of disruption residents have experienced recently.” The review is to examine how the January programme will affect school-run and commuter peaks, along with lane layouts, speed limits and coordination with other roadworks nearby. National Highways, Mr Naish and local councillors have agreed to meet monthly; the agency has not yet said whether the January timetable will change.